We have several updates since our last post informing you that all RAAC had been removed from Club 601 and StAge.

Our new roof is now complete. The tent covers are off and at least from the outside our building is starting to look a bit more like normal!

Tomorrow, Tuesday 23 April will see a 250-tonne crane take down the scaffold truss that supported the temporary roof. So if you are in or around our building please be aware that there may be some change to access and follow any instructions from staff and our building contractors.

Most of the internal scaffolding has now also been removed and we can soon start to put the fun stuff back into StAge & 601 to get it up and running for Freshers’ Week 2024. This includes a new and improved AV, PA & lighting system, extending the length of the bar in 601 and upgrading the sound proofing to reduce noise bleed.